{"id":14980,"date":"2025-09-08T12:44:45","date_gmt":"2025-09-08T10:44:45","guid":{"rendered":"https:\/\/mooc.rfp.cm\/?post_type=courses&#038;p=14980"},"modified":"2025-09-08T10:44:57","modified_gmt":"2025-09-08T10:44:57","slug":"case-study","status":"publish","type":"courses","link":"https:\/\/mooc.rfp.cm\/en\/cours\/case-study\/","title":{"rendered":"Construction and equipping of an office building"},"content":{"rendered":"<p><strong><u>Subject: <\/u><\/strong>Construction and equipping of an office building.<\/p>\n<p>MINEDUB is planning to build a 3-storey building next year, which will be fitted out with office furniture and computer equipment. A wired network will connect all the building&#8217;s computers. This building is a prerequisite for the start of digital educational resource production activities, so it&#8217;s very important that the work proceeds according to schedule<strong><u>.<\/u><\/strong><\/p>\n<p><strong><u>\u00a0<\/u><\/strong><\/p>\n<p><strong><u>Information from the Annual Work Plan (AWP):<\/u><\/strong><\/p>\n<p>The construction of the fully-equipped building is Activity 1 of Action 01 of Program 196 of MINEDUB&#8217;s Annual Work Plan (AWP). The AWP indicates that 480 million euros have been earmarked for this activity. The activity is broken down into 5 tasks:<\/p>\n<table border=\"1\">\n<tbody>\n<tr>\n<td width=\"74\"><strong>Task<\/strong><\/td>\n<td width=\"264\"><strong>description<\/strong><\/td>\n<td width=\"112\"><strong>Paragraph<\/strong><\/td>\n<td width=\"96\"><strong>Cost<\/strong><\/td>\n<\/tr>\n<tr>\n<td width=\"74\">Task 1<\/td>\n<td width=\"264\">Construction of the building<\/td>\n<td width=\"112\">52310<\/td>\n<td width=\"96\">378 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"74\">Task 2<\/td>\n<td width=\"264\">Quality control mission<\/td>\n<td width=\"112\">36131<\/td>\n<td width=\"96\">42 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"74\">Task 3<\/td>\n<td width=\"264\">Purchase of office material<\/td>\n<td width=\"112\">36013<\/td>\n<td width=\"96\">30 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"74\">Task 4<\/td>\n<td width=\"264\">Purchase of computer equipment<\/td>\n<td width=\"112\">36012<\/td>\n<td width=\"96\">20 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"74\">Task 5<\/td>\n<td width=\"264\">Installation of the computer network<\/td>\n<td width=\"112\">5236<\/td>\n<td width=\"96\">10 millions<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<p><strong><u>Information from the Simplified Procurement Plan:<\/u><\/strong><\/p>\n<p>This activity has given rise to a public procurement contract which has been split into 5 lots, one for each task. The contracting process has been completed. All lots have been awarded.<\/p>\n<p>Lot 1 (construction of the building) will be the subject of 3 breakdowns for the construction and 3 breakdowns for the inspection mission.:<\/p>\n<table border=\"1\">\n<tbody>\n<tr>\n<td width=\"317\"><strong>Settlement description\/downward payments<\/strong><\/td>\n<td width=\"130\"><strong>Construction<\/strong><\/td>\n<td width=\"106\"><strong>Contr\u00f4le<\/strong><\/td>\n<\/tr>\n<tr>\n<td width=\"317\">1) Structural work<\/td>\n<td width=\"130\">180 millions<\/td>\n<td width=\"106\">20 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"317\">2) Carpentry-plumbing-electricity-painting-tiles<\/td>\n<td width=\"130\">180 millions<\/td>\n<td width=\"106\">20 millions<\/td>\n<\/tr>\n<tr>\n<td width=\"317\">3) External fittings<\/td>\n<td width=\"130\">18 millions<\/td>\n<td width=\"106\">2 millions<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<p>Construction of the building is scheduled to start in March and last 5 months. Structural work is scheduled for completion at the end of May. External fittings in June, computer networking in July, carpentry-plumbing-electricity-painting in August. Materials and IT equipment are due for delivery in September.<\/p>\n<p>The aim of this case study is to extract the elements needed to draw up a Sector Commitment Plan. For the sake of simplicity, we have limited ourselves to a single activity, but the elements derived from this activity can be generalized to produce a Sectoral Commitment Plan.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Subject: Construction and equipping of an office building. MINEDUB is planning to build a 3-storey building next year, which will be fitted out with office furniture and computer equipment. A wired network will connect all the building&#8217;s computers. This building is a prerequisite for the start of digital educational resource [&hellip;]<\/p>\n","protected":false},"author":2,"featured_media":14981,"template":"","course-category":[24,23,22,21,20,19],"course-tag":[],"class_list":["post-14980","courses","type-courses","status-publish","has-post-thumbnail","hentry","course-category-module-1","course-category-module-2","course-category-module-3","course-category-module-4","course-category-module-5","course-category-module-eng-6"],"_links":{"self":[{"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/courses\/14980","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/courses"}],"about":[{"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/types\/courses"}],"author":[{"embeddable":true,"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/users\/2"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/media\/14981"}],"wp:attachment":[{"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/media?parent=14980"}],"wp:term":[{"taxonomy":"course-category","embeddable":true,"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/course-category?post=14980"},{"taxonomy":"course-tag","embeddable":true,"href":"https:\/\/mooc.rfp.cm\/en\/wp-json\/wp\/v2\/course-tag?post=14980"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}